In with the New
Ile Jeudi
Bob and Lin Griffiths
Mon 7 Apr 2014 17:06
Thursday 27 March to Monday 7 April 2014
Joel returned on Thursday and cleaned the engine room and started
preparations for the new engine. This involved removing the old throttle
and gear change cables and all wiring then detaching the plumbing between our
hot water tank and the heat exchanger in the engine.
A blurred picture of Joel sitting in the engine room about to change the
propeller shaft seal:-
Here you can see the propeller passing through the hull via the black
seal. These seals are critical items, they work hard and can get quite hot
despite being seawater cooled. They have to be replaced about every 500
engine hrs as a precaution. This is normally done with the boat out of the
water but Joel just took off the old seal (which resulted in a lot of seawater
shooting into the boat), then quickly slid the new seal on and bolted it
up. Then he pumped out the water. Do not try this at home! New
seal in place – on the right is the hot water tank:-
The engine room cleaned showing some of the other pipe runs for the hot and
cold water to the galley, heads and aft deck shower (nothing to do with the
engine, they just pass through the engine room):-
In the meantime the marina needed us to move elsewhere but as we had no
engine we had to be towed by one of their dinghies. I manned the wheel and
pretended to be in control.
On Friday more men turned up to lower the new engine on to the boat.
A reverse of the earlier process of course. Lowering in to the
cockpit:-
More bits were taken off to lower through the companionway:-
Then dragged around the galley and lifted into place in the engine
room. Here it is bolted in and the propeller shaft connected but no
pipework or electrics yet. That would have to wait until next week as,
being France, no work is done at the weekend:-
The place was a bit of a bomb site whilst work was done. So we had
been eating out a lot!
We got them to clear up the mess so we could have the boat back for the
weekend and cook and eat on board.
On Monday and Tuesday the installation work continued and the new batteries
were fitted. They are not all very accessible underneath the snakes
nest:-
One disadvantage with the new engine is that it rotates in the opposite
direction to the old one. This means we have to lift the boat to change
the settings on the propeller so that it will work! So on Wednesday we had
the boat lifted for a couple of hours to do this and make some other
adjustments. Then back in the water to do a commissioning run. There
were a number of things arising which was to be expected and these were resolved
by the following Monday.
|