New Decks!
12th February 2009 - Auckland. And so it is we charge headlong into February 09 uncertain
as to how it was that 08 disappeared so fast! After a passage to Fiji on Woody’s 56ft Cat
“Twin Image” in May, (itself an interesting experience for a
non-cat sailor with winds a for couple of days up to 50 kts.), we got into a
winter that reminded me why it is requisite to be out of this country at least between
June and September. This year it wasn’t to be however because this was
Splash Tango’s “birthday” year! She finally went into a shed at Westpark Marine Services
in late June to have the old teak decks removed and new 12mm teak decks fitted.
She was supposed to be back in the water late September. Splash Tango in her pyjamas. I could write a tome of the dramas that unfolded but
suffice to say that anyone who has done a refit of any description knows that
it will never go according to plan or budget. With staff leaving en mass due to
new management and inexperience in the work being done, (half of the new decks
had to be ripped off because the king plank had been laid incorrectly), we were
in fact very lucky to be in the water before Christmas. You have to be there
every day otherwise things will turn pear shaped faster than one can imagine.
We made it though, a week before Christmas, on the 18th Dec. Although
we had intended to set of on our summer cruise that weekend we still then had
to commission the new Genset – a Northern Lights 5 kw and the new AC
watermaker pump motor, fit the new dodgers and fit the 70 headlining panels
that I had re-vinyled, install the new bench top, re-gas the refrigeration
system, do some remedial plumbing work and some other repairs like the anchor
winch and autopilot. When one electrician asked me what was the time frame and I
said “Before New Year.” He just laughed and said
“You’ll kill yourself. Do yourself a favour and put it (the cruise)
off ‘til February”. I said “Not an option”. Anyway we did make it and cast off on new years eve and
headed for Kawau. Man did that first beer taste good! Below are a few photos of the transition. Old decks ready to come off June
’08 – at this stage I had stent 3 weeks below decks removing all
the head lining panels and cabinetry where necessary and removing nuts (most
fibre-glassed in – see photo below) from genoa tracks etc. Note the state of the genoa tracks and
deck below them – no wonder I was getting a few niggling leaks over the
nav station. 12th Oct and at last a small
burst of progress. At this stage there had been no work done for a month due to
most of the staff having left. Also the side decks, most of which had been laid
have been removed again due to an error in the laying of the king plank
forward. 15th November and after
another burst of inactivity for a few weeks we are away again with the side
decks finally being laid. 15th November again looking
aft (obviously). 30th November and we’re
getting there – rubber, steering pedestal, tracks etc to go… 10th Dec. tracks are on
hatches and fittings being replaced and remedial rubber work carried out. 15th Dec. 08 – nearly
ready for a splash! The end result!! __________ Information from ESET NOD32 Antivirus, version of virus signature database 3895 (20090227) __________ The message was checked by ESET NOD32 Antivirus. http://www.eset.com |